Posted on December 12, 2017
The works include the design, supply, manufacture, installation, testing and commissioning of a Sludge Storage and Handling System for Riverstone Waste Water Treatment Plant and St Marys Water Recycling Plant. The project contains 3 main work packages, these include:

Works Package 1
Sludge Storage System for Riverstone Waste Water Treatment Plant comprising:
• Part 1A: Sludge Silo Loading Conveyors
• Part 1B: Sludge Silo
Works Package 2
Sludge Handling System for Riverstone Waste Water Treatment Plant comprising:
• Part 2A: Dewatered Sludge Belt Conveyor
• Part 2B: Sludge Silo Out-loading Belt Conveyor
• Part 2C: Truck Loading Screw Conveyor
Works Package 3
Sludge Storage System for St Marys Water Recycling Plant comprising:
• Part 3A: Silo Distribution Conveyor System
• Part 3B: Storage Silos with Screw Conveyors
• Part 3C: Out-loading Conveyor System
• Part 3D: Inclined Belt Conveyor System
Progress
The design stage is almost 100% complete with fabrication and site works at the St Marys site well underway. Construction of the St Marys plant is scheduled for completion in April 2018. The Riverstone plant will follow and is expected to be complete in August 2018.